Australian electricity and gas markets – April 2026 Update
The reform agenda continues to roll forward. We have highlighted the many reforms published in March that affect the energy sector.
The big news is:
The AEMC is targeting the connection of data centres (and other large inverter based loads) to the national grid and imposing significantly more onerous obligations on the connection.
Implementation of the NEM Review recommendations remains on track (but still not in Queensland). The Department of Climate Change, Energy, the Environment and Water has confirmed:
On 12 March 2026, the Australian Energy Market Commission (AEMC) published a consultation paper seeking feedback on two rule change requests relating to the current frameworks for system security in the National Electricity Market (NEM).
The two rule change requests are as follows:
The rule change requests raise issues about the effective operation of the current frameworks while the power system is in a period of rapid change. Changes in network configuration, generation mix or operating conditions may materially alter the required security services.
The requests address the following:
The rule change requests are a part of a range of programs on supporting system security through the energy transition, such as the AEMC's (in-progression) National System Security Action Plan.
Submissions are due 16 April 2026.
On 12 March 2026, the AEMC released a draft determination and draft rule, being the Draft National Electricity Amendment (Improving the NEM access standards – Package 2) Rule 2026, proposing new technical standards for large inverter based loads such as data centres connecting to the NEM. There is a concern that with the rapid growth of Australia's data centres comes unclear technical standards, and as a result grid stability could be adversely impacted.
The AEMC says the draft rules propose three key changes:
The AEMC has "glossed over" some key implications for the large inverter based loads:
AEMO will be publishing interim guidelines in the coming months to help stakeholders prepare for the new standards.
Submissions close on 7 May 2026. A final rule is expected to be published in mid-2026.
On 19 March 2026, the AEMC initiated an expedited process for a rule change request submitted by AEMO on 17 February 2026. The rule change request is seeking to make small changes improving the operation of the Integrating Price-responsive Resources rule.
The five proposed changes are to:
Submissions for feedback close 16 April 2026.
On 19 March 2026, the AEMC released a consultation paper seeking feedback on a rule change request aimed at improving compensation frameworks. AEMO submitted the request on 27 November 2025. The proposed major changes include:
AEMO considers that the rule change will provide confidence to market participants about appropriate compensation during times of market stress, and to stakeholders that the electricity system will continue to operate despite disruption, as well as reducing the cost and effort of the claims process.
Submissions are due 30 April 2026.
On 19 March 2026, the AEMC released a Directions Paper proposing updates to the rules that govern how gas distribution networks are regulated. As household and small business energy choices shift, such as customers leaving the gas network, the updates the AEMC are proposing ensure the regulatory framework keeps pace.
The proposal is a balanced package of targeted reforms across four areas of the National Gas Rules (NGR):
A public forum is being held on 9 April 2026, with stakeholder registration available here.
Submissions for stakeholder feedback are due 30 April 2026.
On 26 March 2026, the AEMC published a consultation paper to seek stakeholder views on allowing AEMO to accept cash as credit support in the NGR in response to a rule change request from Delta Electricity.
In the NGR, Market Participants in the Declared Wholesale Gas Market (DWGM) and Trading Participants in the Short Term Trading Market (STTM) are required to provide an acceptable form of financial security to AEMO. This provides financial assurance to AEMO in case a participant defaults. Currently, the only acceptable forms of security are bank guarantees or another immediate, irrevocable and unconditional commitment in a form acceptable to AEMO.
Delta Electricity identified that this requirement could be restrictive for Market and Trading Participants that are unable to obtain such guarantees, and submitted a rule change request on 28 July 2025 to allow AEMO to also accept cash as credit support.
Delta considers that while participants did not face barriers in obtaining bank guarantees historically, there has been an increasing trend of financial institutions no longer providing credit support to participants with exposure to fossil fuels, for example coal and gas-fired electricity generation and coal mining. Delta perceives a real risk that a market participant, while being a profitable and solvent business, may be unable to provide credit support to AEMO.
Submissions to the consultation paper close 30 April 2026.
On 5 March 2026, the AEMC released a draft determination to improve the existing processes of retailers and distributors in registering and serving customers with life support equipment at their households.
SA Power Networks and Essential Energy submitted the rule change request on 23 August 2024 following the Energy Charter's #BetterTogether Life Support Customer initiative and consultation.
The draft rule proposes several improvements to how energy retailers and networks register and communicate with life support customers:
Feedback is open until 16 April 2026, with a final decision expected in June 2026.
On 18 March 2026, the AER published a consultation paper seeking feedback on the Retailer of Last Resort (RoLR) guidelines and plan, including:
The AER is seeking submissions until 17 April 2026.
On 19 March 2026, the AER released the draft decision on the Default Market Offer (DMO) for 2026-27.
The price determination applies to residential and small business customers across New South Wales, South East Queensland and South Australia. The DMO caps the prices a retailer can charge a standing offer customer and also serves as a comparison price for market offers in these regions.
The draft decision proposes reductions in DMO prices across all regulated regions, driven largely by lower wholesale electricity costs and reduced environmental and retail operating costs.
If adopted in the final determination, DMO annual prices for residential customers would fall by between 1.3% and 10.1%, while small business prices would decrease by between 7.6% and 21.2%, depending on the region.
The draft determination is open for consultation until 9 April 2026.
On 25 March 2026, the AER released draft Annual Information Orders for 2026-27 and 2027-28 for public consultation with the intent to replace the Orders currently in place for those reporting years with improved processes for electricity network businesses.
The Orders impose annual reporting obligations on regulated electricity distribution networks, transmission networks, and interconnectors.
The changes aim to reduce the volume and complexity of issues arising in future information reporting processes. The proposed updates:
Submissions are open until 11 May 2026.
On 25 March 2026, the AER commenced a targeted review of the Forecasting Best Practice guidelines and published the proposed amendments for consultation.
The Forecasting Best Practice guidelines set out requirements for AEMO's forecasting for reliability assessments and the Integrated System Plan (ISP).
The review proposes the following changes to the guidelines:
Submissions are open until 24 April 2026.
On 26 March 2026, AEMO released the 2026 Victorian Gas Planning Report Update. The Update provides information about the supply demand balance over the next five years in Victoria and the Victorian Declared Transmission System.
Some key points in the update include:
On 26 March 2026, AEMO released the 2026 Gas Statement of Opportunities (GSOO) for Australia's East Coast Gas Market. The publication forecasts the adequacy of gas supplies in central and eastern Australia, based on information provided by gas industry participants, to meet households' and businesses' changing energy needs to 2045.
The GSOO shows improved near-term supply conditions, with risks of extreme peak-day shortfalls in southern Australia now expected to emerge a year later than previously forecast, and new investment required from 2030 onwards.
Total gas consumption is forecast to decline as households, businesses and industry electrify, reducing their reliance on gas. In the NEM, gas‑powered generation demand is also expected to fall below previous forecasts, driven by around 30 gigawatts of battery storage under development and the delayed retirement of the Eraring Power Station.
Despite improved peak-day supply expectations, gas production from legacy fields in southern states is forecast to decline by 46% over the next five years. This will require new investments to address emerging supply gaps from 2030 under most weather conditions.
In March 2026, all NEM jurisdictions except Queensland agreed on how to address the rest of the review’s recommendations. The details are available in the document, National Electricity Market Wholesale Market Settings Review (NEM Review) Recommendations – Implementation Pathways.
This document confirmed the following key items:
On 13 March 2026, the ERA published its final determination for the Benchmark Reserve Capacity Prices (BRCPs) to apply in the 2028/29 Reserve Capacity Year. AEMO will use these BRCPs to determine the price paid to capacity providers in the WEM.
The ERA has determined both the Peak Benchmark Reserve Capacity Price and Flexible Benchmark Reserve Capacity Price to be $488,500 per Megawatt (MW) per year, which is 35% higher than the 2025 BRCP of $360,700 per MW per year. The increase is due to using a longer duration battery energy storage system as the Benchmark Technology, significant increases in labour, materials and freight costs, as well as the new Fixed Capital Charge ($100,000 per MW) that is expected to be in place by 1 July 2026. The Fixed Capital Charge will be used to cover the costs for shared network transmission assets (for new and upgraded generation and load connections over 10 MW in size).
The 2026 BRCP values came into effect on 16 March 2026 and will apply to the 2028/29 Reserve Capacity Year.
On 16 March 2026, AEMO published a Procedure Change Proposal to propose amendments to the WEM Procedure: Settlements. The proposal seeks to update the way in which AEMO distributes civil penalty amounts following changes to the ESM Rules that came into effect on 1 January 2026, specifically to require that civil penalties are distributed in accordance with instructions provided by the ERA.
Submissions in response to this Procedure Change Proposal are due via email to WA.Marketdevelopment@aemo.com.au by 16 April 2026 using the provided Procedure Change Submission form.
On 17 March 2026, the Coordinator of Energy published his Final Rule Change Report for Rule Change Proposal RC_2025_01.
The Rule Change Proposal submitted by Bluewaters Power proposed a change to the eligible sources of supplementary capacity that are Eligible Services under clause 4.24.3 of the ESM Rules. The proposal sought to allow the production of electricity by Energy Producing Systems that are Registered Facilities – and for which the relevant Market Participant applied for certification in the current Reserve Capacity Cycle but were not awarded Capacity Credits – to participate in the supplementary capacity process in the Capacity Year for which they did not receive Capacity Credits.
The Coordinator’s final decision was to reject the Rule Change Proposal on the basis that it was inconsistent with the State Electricity Objective. For a more detailed explanation of the Coordinator's reasons, see section 2.1 of the report.
On 23 March 2026, the ERA published its draft determination of the Frequency Co-optimised Essential System Services (FCESS) Offer Price Ceilings, which cap the price of FCESS offers in the Real-Time Market. The ERA has employed a new method to calculate the FCESS Offer Price Ceilings based on real market data and operational information of the FCESS markets.
The proposed FCESS Offer Price Ceilings in the draft determination are:
| Service | Offer price ceiling |
|---|---|
| Regulation Raise | $250/MW/h |
| Regulation Lower | $300/MW/h |
| Contingency Reserve Raise | $250/MW/h |
| Contingency Reserve Lower | $50/MW/h |
| Rate of Change of Frequency Control Service | $0/MWs/h |
The ERA is also proposing to remove the process of rounding up to the nearest $50 per MW per hour for newly indexed FCESS Offer Price Ceilings and to instead round up to the nearest $1 per MW per hour.
Submissions on the draft determination are due by 21 April 2026.
In early March 2026, PoweringWA released the Community Benefits Guideline for Large-scale Renewable Energy Projects in the South West Interconnected System (SWIS).
The Guideline provides a clear framework for effective community benefit arrangements, recommending firm dollar-per-megawatt figures for new grid-connected wind, solar, and Battery Energy Storage System projects connected in the SWIS. These figures balance the commercial priorities of industry with the need for projects to deliver meaningful and lasting benefits to local communities.
While compliance with the Guideline is currently voluntary, it is incentivised through eligibility under the Capacity Investment Scheme. The State Government has indicated an intention to mandate these standards in the future if necessary.
Authors: Dan Brown, Partner; Kate Phillips, Partner; Dale Gill, Partner; Paul Newman, Consultant; Aylin Cunsolo, Partner; Lauren Zambotti, Counsel; Taylah Smith, Graduate; Elisabeth Gregory, Graduate and Jenna Matus, Paralegal.
The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.