Legal development

An ordered queue: reform of the GB grid connections process

power grid

    On 10 June 2025, the set of reforms to the electricity grid connections process – referred to as "Connections Reform" (or the TMO4+ reforms) – went "live". This followed the 15 April 2025 approval by the regulator, Ofgem, of the industry code and licence condition modifications, as well as associated documents, that implement the significant reforms to the grid connections process that have been taken forward by the new National Energy System Operator (NESO). Connections Reform is intended to address the connection delays that resulted from the former "first come, first served" connection applications model, and achieve the goals set out in the Government's Clean Power 2030 Action Plan (CP30 Action Plan). Significantly, Connections Reform has implications not just for new connection applicants, but also for most projects that currently hold a connections offer to connect to the transmission or distribution system.  

    In this briefing we set out a summary of the key elements of the reforms, implications for different categories of projects and the timetable for implementation of the reforms.

    The new regime in a nutshell

    Under the new grid connections regime most projects seeking a new connection (or a modification to an existing connection) to the transmission or distribution system will no longer be able to apply at any time to secure a place in the connections queue. Instead, there will be set application windows. To secure a place in the queue, applicants will need to meet certain Gate 2 criteria. Applicants that are unable to satisfy the Gate 2 criteria may be eligible for a Gate 1 connection offer, which serves to provide only indicative connection details.

    The Gate 2 criteria, set out in the Gate 2 Criteria Methodology, are made up of two elements:

    • Gate 2 Readiness Criteria; and
    • Gate 2 Strategic Alignment Criteria.

    The only projects not impacted by Connections Reform (referred to by NESO as "out of scope") are: 

    • existing connected parties that have already energised;
    • demand projects seeking a connection to the distribution system; and 
    • generation projects seeking a connection to the distribution system that do not require Transmission Impact Assessment (TIA) (as these have no significant impact on the transmission system). The TIA threshold applying in England and Wales was recently raised from1 1MW to 5MW, but remains 200kW in Scotland South and Scotland North. However, even though the general threshold was raised to 5MW for England and Wales, there may be some projects below 5MW but at 1MW or above that are impacted because the relevant Grid Supply Point (GSP) does not have sufficient fault level headroom.2

    Before the enduring arrangements commence, NESO will carry out a one-off exercise – the "Gate 2 to Whole Queue" (G2TWQ) process – to determine which projects that currently hold a connection offer satisfy the Gate 2 criteria.  Following the G2TWQ process, projects that have been subject to it will receive either a Gate 2 offer or a Gate 1 offer.

    Recognizing that the G2TWQ process will apply retrospectively to many connection offer holders, projects that currently have a connection offer and that fall within certain exceptions or "protections" (set out in more detail below) will be considered to satisfy the Strategic Alignment Criteria.

    In terms of the general architecture of the new regime, the following are its key elements:

    • amendments to the Connection and Use of System Code (CUSC), through code modification CMP435, to implement the G2TWQ process (primarily through a new section 18 of the CUSC);
    • amendments to the CUSC, through code modification CMP434, to implement the enduring arrangements (primarily through a new section 17 of the CUSC);
    • amendments to the System Operator Transmission Owner Code, through code modification CM095;
    • three new documents (referred to as methodologies) which NESO is now required to maintain pursuant to its licence. These are: 
      • the Gate 2 Criteria Methodology;
      • the Project Designation Methodology; and 
      • the Connections Network Design Methodology; and
    • associated licence condition amendments.

    Timetable

    NESO has published a full timetable for implementation of Connections Reform on its website.3 The key dates from that timetable are as follows.

    20 May 2025

    Distribution Network Operators (DNOs) start to accept Gate 2 evidence submissions (for the G2TWQ process) from existing distribution connection offer holders.

    10 June 2025

    Following a 56 day "standstill" period for the changes to take effect, the new regime goes "live"

    8 July-29 July 2025

    The NESO Gate 2 evidence submission window opens, closing on 29 July 2025. NESO will receive evidence submissions from:

    • transmission connecting offer holders;
    • DNOs on behalf of small and medium generators that have made their evidence submissions to the DNO;
    • large distribution generation projects with a BEGA or BELLA4 .
    September 2025 Transmission connection customers will start to receive notifications from NESO about the outcome of the G2TWQ process.
    October 2025 Distribution connection customers will start to receive notifications from their DNO about the outcome of the G2TWQ process.
    End of 2025

    The second Gate 2 window is expected to open – this will be the first window under the enduring regime (as opposed to G2TWQ).

    Mid 2026 The third Gate 2 window is expected to open.
     

    Arrangements pending full implementation of the connections reform

    Transitional Offers

    In preparation for implementation of the new regime, since 2 September 2024, any new applications for a direct connection to the transmission system received a so-called "Transitional Offer". These Transitional Offers have been similar in nature to the "Gate 1" offers being introduced as part of the connections reforms (see below). In particular, Transitional Offers have only included an indicative connection date and an indicative connection location. As the application will not have been studied, no reinforcement works have been included or associated securities required.

    The Transitional Offers process was not applied to BEGA, BELLA or modification applications.

    The application "pause"

    On 15 January 2025 NESO announced a "pause" on accepting new applications from 29 January 2025 (subject to some exceptions). The pause no longer applies, although, as explained below, under the new regime, projects within the scope of Connections Reform (that do not already hold an offer) will have the next opportunity to apply for a connection when the second Gate 2 window is opened by NESO.

    The Gate 2 Readiness Criteria

    The applicant, through a Readiness Declaration, will be required to provide evidence that the project is "ready" by demonstrating compliance with the Readiness Criteria, which can be demonstrated through one of the following two routes: the project acquiring appropriate land rights or going through the Development Consent Order process – as summarised in Figure 1. The full details are set out in the Gate 2 Criteria Methodology. These two possible ways of satisfying the Gate 2 Readiness Criteria are also described as the "land route" and the "planning route".

    Figure 1: Gate 2 Readiness Criteria

    Route for satisfying Readiness Criteria

    Details

    Land

    Applicant must:

    • meet minimum acreage requirements, which relate to 100% of the land required for the project (calculated using the Energy Density Table) (or offshore equivalent);
    • provide original red line boundary for site on which project is located; and
    • have secured land rights (whether by option, existing ownership or land lease).

    Planning

    Applicant must have a submitted and validated application for planning consent in accordance with the Development Consent Order process, which allows the applicant to be granted Compulsory Purchase Order powers.

    The Gate 2 Strategic Alignment Criteria

    The Government's CP30 Action Plan plays a key role in establishing the Strategic Alignment Criteria.  

    The Connections reform annex of the CP30 Action Plan sets out the capacity ranges for the main technologies that are expected to be deployed to allow the clean power objectives to be met, and which will therefore inform the prioritisation of projects for grid connection. As well as setting out the capacity ranges for the period up to 2030, the annex also sets out indicative capacity ranges for the period up to 2035. See Figure 2 below for the 2030 capacity ranges.

    Figure 2: 2030 capacity ranges

    Technology

    Offshore wind

    Onshore wind 

    Solar

    Nuclear

    Low Carbon Dispatchable Power

    Unabated gas

    LDES

    Batteries

    Interconnectors

    Current installed capacity (GW)

     14.8

     14.2

     16.6

     5.9

     4.3

     35.6

     2.9

     4.55

     9.8

    Clean Power Capacity Range (GW)

     43-50

     27-29

     45-47

     3-4

     2-7

     35

     4-6

     23-27

     12-14


    For most projects (in particular, the technologies covered by the CP30 Action Plan), the primary way of satisfying the Strategic Alignment Criteria will be through alignment with the generation technology capacities set out in the CP30 Action Plan – in effect, by fitting within the relevant "technology pots", as described in more detail in Figure 3. However, there are also other ways that projects can satisfy the Strategic Alignment Criteria, including protections for projects currently being progressed.  

    The different routes to satisfying the Strategic Alignment Criteria are summarised in Figure 3, with full details set out in the Gate 2 Criteria Methodology.

    Figure 3: Routes to satisfying the Strategic Alignment Criteria

    Route to satisfying the Strategic Alignment Criteria

    Key document

    Details

    Certain "protections" for existing connection offer holders

    Gate 2 Criteria Methodology

    Projects relying on this route will need to fall within one of the following categories (described as "clauses"):

    • Clause 1: projects contracted to connect by the end of 2026 and which have met certain queue management User Progression Milestones (M2 and M7);
    • Clause 2a: projects which are "significantly progressed", where this can be evidenced by one of the following ways prior to the closure of the G2TWQ application window:
      • having obtained planning consent, where the planning application was submitted on or before 20 December 2024 and subsequently validated (except where the project does not require planning consent, but has met queue management User Progression Milestone 7 (M7));
      • holding a "live" Contract for Difference;
      • holding a "live" capacity agreement;
      • for LDES and interconnectors/offshore hybrid asset projects, having obtained approval from Ofgem, in the form of either a cap and floor agreement or merchant interconnector approval; or
      • holding a "live" contract with NESO awarded through the "Network Services" process (previously referred to as "NOA Pathfinders");

    Projects eligible for protection under Clause 1 and Clause 2a (where their connection date is on or before 31 December 2027) will retain their existing connection date and point of connection. Other projects eligible for protection under Clause 2a will retain a place in the queue but will be subject to a reassessment to determine their final queue position and connection date.

    • Clause 2b: projects which are significantly progressed (and reapply under the enduring process, as opposed to the G2TWQ process), where this can be evidenced by one of the following ways before the closure of the relevant application window:
      • holding a "live" Contract for Difference;
      • holding a "live" capacity agreement;
      • for LDES or interconnectors/offshore hybrid asset projects, having obtained approval from Ofgem, in the form of either a cap and floor agreement or merchant interconnector approval; or
      • holding a "live" contract with NESO awarded through the "Network Services" process (previously referred to as "NOA Pathfinders");
    • Clause 3a: projects which submitted an application for planning consent on or before 20 December 2024 and have not obtained planning consent before the closure of the G2TWQ application window – these projects, if they do not meet the Strategic Alignment Criteria, can reapply in a future application window (under the enduring regime) once they obtain planning consent and will be eligible even if they exceed the permitted capacities for the relevant technology; and  
    • Clause 3b: projects which submitted an application for planning consent on or before the closure of the G2TWQ application window – these projects, if they do not meet the Strategic Alignment Criteria, can reapply in a future application window (under the enduring regime) once they obtain planning consent and will only be required to fit within the GB total permitted capacity for the relevant technology, even where there is a zonal permitted capacity outlined for the technology and this is exceeded.

    CP30 Action Plan

    Connections reform annex of CP 2030 Plan

    This applies to offshore and onshore wind, solar, nuclear, low carbon dispatchable power, unabated gas, Long Duration Energy Storage (LDES), batteries, interconnectors.

    Projects will need to fall within the capacity ranges set out in the plan for individual technologies, for Phase 1 (2026-2030) and Phase 2 (2031-35). These capacity ranges are GB-wide, except for solar, onshore wind and batteries – for these technologies, the capacity ranges are set for 11 transmission zones and 8 distribution zones (noting that for onshore wind and solar, the zonal split only applies for Phase 1, and for Phase 2, amalgamated transmission and distribution network capacities apply). Where there is under-supply against capacity ranges up to 2030, NESO will look first to substitute viable projects of the same technology from adjacent, over-supplied, zones.

    Designation in accordance with the Project Designation Methodology

    Project Designation Methodology

    Certain projects can satisfy the Strategic Alignment Criteria by making an application to be designed by the NESO if they fall within one or more of the following categories:

    • A. projects that are critical to security of supply;
    • B. projects that are critical to system operation;
    • C. projects that materially reduce system and/or network constraints (this could, for example, be large demand projects or long duration storage located in a beneficial location in terms of materially reducing system or network constraints created by large volumes of generation);
    • D. projects that are new technologies and/or highly innovative, that are not included within the scope of the CP30 Action Plan or do not correspond with a technology that has been deemed by NESO to have met the strategic alignment criteria; and/or
    • E. projects with very long lead times, that may be needed beyond the 2035 capacities within the CP30 Action Plan.

    For categories A to C, NESO will publish a notice when it considers that projects within those categories are needed.

    For categories D and E, projects will be able to apply at any time to NESO for a designation. However, NESO has stated that it only envisages designating projects in "exceptional" circumstances.

    Projects not within the scope of the CP30 Action Plan, but which are listed in section 6.3 of the Gate 2 Criteria Methodology

    Gate 2 Criteria Methodology

    The following categories of projects are outside of the scope of the CP30 Action Plan and are considered to automatically meet the Strategic Alignment Criteria:

    • transmission-connected demand;
    • wave;
    • tidal;
    • run-of-river hydro;
    • geothermal power; and
    • non-GB generation.

     

    The CP30 Action Plan, first published in December 2024 and updated in April 2025, will in the future be replaced by longer-term plans for the GB energy system, as summarised in Figure 4. Significantly, the Infrastructure and Planning Bill (currently before Parliament) includes provisions which explicitly link the connections process to strategic plans designated by the Secretary of State pursuant to regulations contemplated by the Bill.

    Figure 4: Longer-term energy plans

    Strategic Spatial Energy Plan (SSEP)

    This will be developed by the NESO to spatially map out the energy assets necessary to meet 2050 objectives, building on the CP 2030 Plan. This is due in 2026.

    Centralised Strategic Network Plan (CSNP)

    In parallel with the SSEP, the NESO will develop a gas and electricity transmission network plan out to 2050. The CSNP is due in 2027.

    Regional Energy Strategic Plans (RESPs)

    The SSEP will also interact with and inform RESPs – and vice versa.

    Gate 2 to Whole Queue

    As mentioned above, the G2TWQ assessment process will commence in July 2025.  The Connections Network Design Methodology sets out details of how the G2TWQ process will be carried out.  At a high level, the process will involve the following:

    • projects are eliminated if they do not meet the Gate 2 Readiness Criteria or have not been selected for Connection Point and Capacity Reservation (a process by which NESO may reserve connection points and capacity for certain projects – e.g. CATOs);

    • remaining projects are eliminated if they do not meet the Gate 2 Strategic Alignment Criteria. Depending on when the relevant projects are able to connect, they will either be considered against the 2030 phase or the 2035 phase. NESO will maintain the existing relative queue positions of projects that align to the 2030 phase. For the 2035 phase, preservation of the original relative queue order is seen as less critical, because the programme of works required to connect these projects will likely require more revision;

    • as part of the G2TWQ process, capacity will be "freed up" by projects that have not met the Gate 2 criteria being removed from the queue. Therefore, alongside submitting evidence that they have met the Gate 2 Readiness Criteria, projects can also submit a modification application and request that their project is considered for advancement as part of the G2TWQ process, as well as changes to their point of connection;

    • Gate 2 offers (which will be "Gate 2 modification offers" in the context of G2TWQ) will be issued by NESO in batches, to successful projects. To retain their Gate 2 offer, projects will then need to continue to comply with the conditions of the offer, including any milestone requirements, to avoid termination. The User Progression Milestone process has been aligned with Connections Reform, as reflected in NESO's updated Queue Management Guidance;

    • projects that have not been successful in securing a Gate 2 offer will:

      • have their security returned to them; and

      • be issued with a Gate 1 offer (see below) via an Agreement to Vary;

    • for small and medium embedded generators, NESO will issue a Gate 1 offer to the DNO and the DNO will then issue a "Distribution Gate 1 offer" to the customer, that reflects the NESO Gate 1 offer.

    The enduring arrangements

    Following the one-off G2TWQ process, NESO will hold Gate 2 application windows twice a year.

    Projects that are unable to satisfy the Gate 2 criteria at the time of application will also have the option of applying for a Gate 1 offer instead.

    Nature of a Gate 1 offer

    A Gate 1 offer will include only an indicative connection date and an indicative connection location (unless the project is selected for Connection Point and Capacity Reservation).  Importantly, an application for a Gate 1 offer is not a prerequisite to a subsequent application for a Gate 2 offer.

    Implications for connections to the distribution system

    For small and medium embedded generators, DNOs will carry out initial checks on whether projects satisfy the Gate 2 criteria and will then follow a process largely based around the Project Progression process that currently applies. The Statement of Works process is being removed, with Transmission Evaluation being introduced as a route for a DNO to request an Evaluation of Transmission Impact. DNOs will submit a Transmission Evaluation Application to NESO on behalf of their embedded customers, within the Gate 2 application window. The application can contain multiple embedded generator projects or one submission per embedded generator project.

    Importantly, for small and medium embedded generators, the NESO will be making the Gate 2 or Gate 1 offer (as the case may be) to the DNO, which will then be reflected in the offer made by the DNO to the relevant customer.

    Large embedded generators will be able to apply for a BEGA/BELLA Gate 2 offer throughout the year, but the DNO will still need to submit a modification application (for transmission assessment) in the Gate 2 application window.  NESO will verify whether a project has met the Gate 2 criteria as part of processing of the BEGA/BELLA application.  If a large embedded generator wishes to receive a Gate 1 offer prior to having met the Gate 2 criteria, it must submit the BEGA/BELLA application to NESO in the Gate 2 application window, but no modification application is needed from the DNO – the large embedded generator will receive a Gate 1 offer from NESO based on their BEGA/BELLA application.

    New Progression Commitment Fee

    As part of Connections Reform, NESO has also been considering the introduction of a new requirement for Gate 2 offer holders to provide financial security, to further signal their commitment to progressing their project.  NESO published a "call for input" on these proposals in November 2024.

    Following this call for input, NESO raised a new CUSC modification (CMP448) to introduce a Progression Commitment Fee (PCF) that will support future connections in the queue. The PCF will only apply to generation projects that have already progressed through the first stages of the connections process to join the future Gate 2 connections queue but have not yet initiated statutory consents and submitted a planning permission which is a requirement of Milestone 1 (which is one of the "User Progression Milestones" referred to above). 

    Under the proposals, NESO has indicated that the PCF will remain dormant unless a metric, which is indicative of the health of the connections queue exceeds a defined threshold. The proposed PCF applicable to a project will have an initial value of £2,500/MW, increasing at a rate of £2,500/MW at 6 monthly intervals up to a maximum of £10,000/MW for any individual project.  Projects will be liable for the full value of their PCF upon termination of the project (or the appropriate portion of the PCF upon reduction of capacity) prior to successfully demonstrating achievement of Milestone 1.

    If the PCF is activated, developers of projects between Gate 2 and Milestone 1 will be required to post a security against the PCF, the “Progression Commitment Fee Security” (PCFS). The PCFS must remain in place until the developer successfully demonstrates that the project has achieved Milestone 1. After achieving Milestone 1, developers will no longer be subject to the PCF if they terminate and there will no longer be a requirement to secure against the PCF. 

    This modification has been approved as "urgent" by Ofgem, meaning that it can follow an expedited timetable.  It is proposed to be implemented prior to applicants having to accept their Gate 2 offer.

    Next steps

    All existing connection offer holders, as well as future applicants, need to familiarise themselves with the new regime.  This is particularly important for existing connection offer holders who will need to submit an application as part of the G2TWQ window – these projects need to be ready to submit their application to the relevant DNO or NESO (as the case may be).  NESO is currently holding various industry webinars and has published various guidance on the process on its website.

    This is an updated version of a briefing previously published in February 2025.

    Authors: Justyna Bremen, Counsel; Antony Skinner, Partner; Hannah Roberts, Associate


    1. This change was implemented through a modification to the CUSC – CMP446 – which took effect on 12 May 2025.
    2. NESO's Connections Reform Evidence Submissions Handbook includes a full list of GSPs that remain at the existing 1MW TIA threshold.
    3. See the full timetable here: https://www.neso.energy/industry-information/connections-reform
    4. These are applications for a Bilateral Embedded Generation Agreement (BEGA) or a Bilateral Embedded Licence Exemptible Large Power Station Agreement (BELLA) under the Connection and Use of System Code (CUSC).
    5. Project Progressions, similarly to Statements of Works, are the documents submitted by DNOs to NESO to inform the NESO about the impact on the transmission system of new connections to the distribution system.
    6. "Clock start" is a reference to the date on which the application and Data Registration Code (DRC) data submission is deemed technically competent, and the fee is paid (the latter of the two dates). Clock start signifies the start of the 3-month offer period as defined in CUSC.

    The information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
    Readers should take legal advice before applying it to specific issues or transactions.