Contract formation and the dangers of letters of intent
We consider the English law on contract formation and the issues that often arise with letters of intent, in light of two recent cases.
What you need to know
Letters of intent can serve a useful purpose, as a sign of commitment to a project. They may also be the basis for some initial work to be done, such as ordering long-lead items. There is a risk, however, that they may be more than the parties had bargained for: if in the end the final contract is not signed, a court or an arbitral tribunal might conclude that the letter of intent was binding after all. This can mean that a simple contract may have been formed that is unsuitable for the project.
Like all transactional documents, parties need to be careful that a letter of intent has a clearly defined scope and purpose. In particular, it should state that it is not intended to be binding, if that is what the parties mean. The parties must then behave consistently with that statement.
The cases
Arcadis Consulting (UK) Ltd (Formerly Hyder Consulting (UK) Ltd) v AMEC (BCS) Ltd (Formerly CV Buchan)1 related to the construction of a car park at a shopping centre in Bournemouth, UK. The defendant, Buchan, was the specialist concrete sub-contractor. It engaged the claimant, Hyder, to carry out design works. The car park developed serious faults: cracks appeared in the concrete, and some concrete fell off. The car park may need to be rebuilt at the cost of tens of millions of pounds. The contractor blamed Buchan, which in turn blamed Hyder.
Hyder argued it was not liable for the defects; but if it was, its liability was limited to around £600,000. For this limitation of liability it pointed to various contract documents which passed between Buchan and Hyder but were never signed. In fact, while Buchan had issued a letter of intent instructing Hyder to start work, no formal contract was ever executed. Buchan argued that no contract was formed at all. The judge rejected that submission, and concluded that, as the work had been carried out and completed, a contract had been formed. However, he also concluded that, since the limitation of liability proposed by Hyder had not been accepted by Buchan, the contract did not contain such a term. Buchan could therefore pursue Hyder for the full amount of the loss.
Spartafield Ltd v Penten Group Ltd2 concerned an extension to a building in east London, to add eight new flats. Spartafield was the developer and Penten was the contractor. A letter of intent was issued: it was originally supposed to just cover the cost of design and pre-construction activities, but eventually covered all work up to the cost of £ 1 million. Again, however, no final contract was ever executed. The work proceeded, and, towards the end of the project, various claims for additional costs were made by Penten. An adjudicator decided that Spartafield had to make a payment to Penten, by reference to the terms of the letter of intent. Spartafield sought to have that decision set aside because, it submitted, the letter of intent had in fact been replaced, through the conduct of the parties, by a main contract based on the standard terms of the JCT Intermediate Contract with Contractor's Design 2011.
The judge reviewed all the relevant documents that passed between the parties. He concluded that everything had been agreed for the main contract, apart from a few minor details: for example, the parties had agreed on a scope of work, a date for completion, and a contract price. This meant that, although the main contract had not been signed, it had in fact been formed, replacing the letter of intent.
Why are these cases of interest to the energy sector?
These two cases highlight the potential risks involved in carrying work out before a formal agreement containing all the terms agreed by the parties has been finalised and executed. Although both cases are fact-specific and concern the UK construction industry, they are of wider application.
Letters of intent or memorandums of understanding are frequently used in the energy sector, with finalised contracts to be agreed upon after further negotiations. Parties may be under internal or external pressure to start work before they have signed the contract, so they sign a letter of intent in order to get work underway.
These can give rise to binding obligations – and in some cases that is what is intended. For example, there might be a mobilisation of drilling equipment to a drill site while the full terms of the project documents are being negotiated. The letter of intent may cover the mobilisation of the equipment and payment for it.
However, in some situations, there may be unintended consequences flowing from letters of intent, particularly when a party thinks that a contract has not yet been formed.
When is a contract formed?
This issue arose in the Arcadis case. The judge referred to the ruling of the UK Supreme Court in RTS Ltd v Molkerei Alois Muller GmbH & Co3, which said that whether there is a binding contract between the parties depends on:
"[A] consideration of what was communicated between [the parties] by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations."
This means that a contract can be formed regardless of the fact that the parties intend to draw up and sign a detailed agreement in the future. And if the transaction is actually performed on both sides (by the conduct of work, and payment for this), that will usually make it unrealistic to argue that no contract has been formed.
What are the terms of the contract?
A letter of intent usually contains little detail. This means that if a court or an arbitral tribunal concludes that a contract has been formed, it is likely to be a simple contract, lacking the detailed terms that cover every aspect of the project. This was the case in Arcadis, where the judge found that the contract that was formed did not contain the limitation of liability proposed by Hyder. The judge said4:
"Whilst the court should always strive to find a concluded contract in circumstances where work has been performed… the court is not entitled to rewrite history so as to incorporate into that contract express terms which were not the subject of a clear and binding agreement."
Where does the letter of intent and the main contract start?
Spartafield discussed the boundary between a letter of intent and the main contract. This may be crossed, with the main contract coming into force, even without the main contract being signed. The judge or arbitrator will need to review all the facts and decide whether, on an objective view of all the circumstances, the main contract has been formed.
How can parties protect themselves?
There are five things that parties can do:
- As the judge in Spartafield noted, if parties do not intend to enter into a contract at the outset, they can expressly state that the signing of the detailed agreement is a precondition to forming a contract.
- They can mark their correspondence, and any draft contracts, "subject to contract". This applies both to the letter of intent and to the lead-up to the main contract.
- They can be clear about what the letter of intent covers – for example, only the purchase of long-lead items.
- They can act consistently with this. The judge in Spartafield pointed out (relying on the Supreme Court ruling in RTS) that even express "subject to contract" wording can be overridden by the parties' conduct, if their conduct amounts to a waiver of that term.
- They can wait until the main contract is signed. As the judge in Arcadis stated: "This case starkly demonstrates the commercial truism that it is usually better for a party to reach a full agreement … through a process of negotiation and give-and-take, rather than to delay and then fail to reach a detailed agreement at all."
1. [2016] EWHC 2509 (TCC)
2. [2016] EWHC 2295 (TCC)
3. [2010] 1 WLR 753
4. At paragraph 48.
Keep up to date
Sign up to receive the latest legal developments, insights and news from Ashurst. By signing up, you agree to receive commercial messages from us. You may unsubscribe at any time.
Sign upThe information provided is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.
Readers should take legal advice before applying it to specific issues or transactions.